Implementation Plan
| DateĀ | Team Members | Actions |
|---|---|---|
| Thu. 11/12 | A. | Install Win. 7, Pinnacle, Open Office, Fire Fox, Flash |
| Fri. 11/13 | A. and G. | Buy equipment, experiment with Win. 7 and Pinnacle |
| Thu. 11/19 | A. and G. | Install Win. 7, Open Office, Fire Fox, Flash and Pinnacle on Desktops |
| Fri. 11/20 | A., G., AB2 section | AB2 lab section will secure Win. 7 on computers |
| 11/21-11/29 | Thanksgiving | |
| Thu. 12/3 | A. and G. | Final work on projector, camcorder, digital cameras and mics |
| Fri. 12/4 | ALL | Installation at Salem |