Plan of Execution
The Steps the Organization Needs to Accomplish Prior to Computer Delivery
- Locate and set up tables or desks for computer work surface.
- Empty and paint computer lab.
- Communicate with Building Network Administrator to discover the equipment needed to make the network function for their space.
- Purchase necessary hardware. (router, switches, tables, etc.)
The Steps the Project Team Needs to Accomplish Prior to Computer Delivery
- dBan 7 computers
- Install Linux
- Create user accounts.
- Run auto update script.
- Gather monitors, keyboards, mice, cables.
Potential Risks That Might Hinder Fully Accomplishing the Plan
- Time
- Computer arrangements