| March 15 | All | 1. Completed "Description of Site" wiki page. |
| | 2. Created floor plan using Gliffy and Adobe software. |
| | 3. Uploaded images from site visit to Wiki. |
| | 4. Uploaded contact information to Wiki. |
| March 22 | All | 1. Edited "Description of Site." |
| | 2. Created cover letter. |
| | 3. Faxed "Description of Site" document and cover letter to Mrs. Tolson at Parks Chapel for verification of project. |
| | 4. Exchanged e-mail with Mrs. Tolson. We recieved Parks Chapel federal tax number. |
| March 29 | All | 1. Finalized computer placement in fellowship hall. |
| | 2. Faxed floor plan and cover letter to Mrs. Tolson at Parks Chapel for verification of computer placement in fellowship hall. |
| | 3. Helped to "nuke" computers. Checked donated computers for operating system and functionality. |
| | 4. Attempted to call Mrs. Matory (x2) to find out about computer literacy classes at Parks Chapel. E-mailed Mrs. Tolson to verify Mrs. Matory's contact information. |
| | 5. Started discussions about Internet Service Providers at Parks Chapel. Decided that internet should be up and running by May 1 (at the latest). |
| | 6. E-mailed Adam to see how many comptuers were allocated to Parks Chapel group. |
| | 7. Continued write-up of the Wiki page. |
| April 5 | All | 1. Exchanged e-mails with Mrs. Tolson to verify Mrs. Matory's contact information. |
| | 2. Attempted to call Mrs. Matory (x3) to find out about computer literacy classes. |
| | 3. Searched for Internet Service Providers for Parks Chapel. AT&T and Comcast does not provide Internet in the area. Found that Chater Cable (Internet) will provide Internet--$20/month without a router package available. |
| | 4. $40 (pre-tax) router is available at Best Buy. $100 modem, with a $90 rebate. |
| | 5. Installed Windows XP operating sysetem on five allocated computers. |
| | 6. Added user accounts and adjusted permissions on the Operating systems. |
| | 7. Attempted to call Mrs. Tolson to speak about ISP. |
| April 12 | All | 1. Phone conversation with Mrs. Matory discussing her role as administrator. |
| | 2. Phone conversation with Mrs. Tolsen regarding internet service providers, hardware, and dates of installation. |
| | 3. E-mail to Mrs. Matory regarding software that her daughter (a teacher) might recommend for children's educational use. |
| | 4. E-mail to Mrs. Tolsen regarding a.) Ordering Internet installation by May 1 b.) The purchase of a modem c.) The purchase of a router d.) The tables that will be used in the computer lab. |
| | 5. Installation of software on three of five computers. |
| | 6. Cable making |
| | 7. Meeting with Martin to update on status of the project. |
| | 8. Concept paper consolidation began. |
| April 19 | All | 1. Phone conversation with Mrs. Tolson. Discussed Internet hardware and Internet installation. |
| | 2. E-mail to Mrs. Matory regarding 1) Open Office and 2) Internet hardware and installation. |
| | 3. More cable making. |
| | 4. Software updates. |
| | 5. Progress on manual. |
| | 6. Second e-mail to Mrs. Matory regarding the purchase of power strips. |
| | 7. Editing of manual |
| | 8. Phone call to Mrs. Matory regarding Internet hardware and power strips. No Answer, left a message. |
| April 26 | All | 1. Phone call from Mrs. Matory to Konya: Charter has their own modem that they want the church to use. Mr. Matory will pick up that modem today (4/27). They already have the power strips. She was not sure about the router, but thought from previous communication with Mrs. Tolsen that one of our group members told her that the router is taken care of. She wanted me to say thanks to all of my group members because she is excited about all that we are doing! |
| | 2. Phone call from Peter to Mrs. Tolsen: (1) The Internet will be installed Friday (April 30) from 1 - 3. (2) 5 computer desks will arrive today (4/28). (3) Mrs. Tolsen will speak to Mr. Matory about the router today (4/28). |
| | 3. Installed Microsoft Office on computers. |
| | 4. Purchased two binders, sheet protectors, and dividers. |
| | 5. Updated technical documentation. Printed cover sheets and documents. |
| | 6. Created a "shared folder" on each computer desktop. |
| | 7. Updated wiki. |
| 3-May | All | 1. Parks Chapel site visit! |
| | 2. Set up computers and peripherals in their uber-awesome computer desks. |
| | 3. Set up LAN network, modem, router, switch. |
| | 4. Set up other computers for Parks Chapel. |
| | 5. Cable making back at the Hubbard House. |
| | 6. Took many pictures and updated Wiki. |
| | |
| 4-May | All | 1. LAN network with the new cables. |
| | 2. Completed software updates, reformatting a computer that had issues. |
| | 3. Networked printer to computers. |
| | 4. Finalized Shared Folders. |
| | 5. Pampered by Parks Chapel by lunch, and being a good-looking crew, as Team Awesome is prone to do. |
| | 6. Took more pictures and updated Wiki. |
| 10-May | All | 1. Created PowerPoint slides and devised presentation order. |
| 11-May | All | 1. Finished "Lessons Learned" section of Wiki page. |
| | 2. Practiced for presentation on May 12. |