Implementation Plan
March 20th-26th
Priority: Complete Hardware Inventory, All Computers ready for O/S Install
Due: Communicate with Mt. Calvary regarding project priorities and timeline. Still need print server, XP licenses, server inventory and/or software.
March 27th-April 1st
Priority: Inventory and Plan for Server
Due: 5-10 Educational Web Sites (Peggy links for ages 6-10, Jessica links for ages 12-18, Jessica/Erin for online banking and email, Erin links for the elderly)
April 2nd-9th
Priority: Install O/S, Applications, Security, Drivers
April 10th-16th
Priority: Finish Install, Network and Server Set-up
Due: Network Research
April 17th-23rd
Priority: Network and Server Set-up
Due: Floor plan (Jessica)
April 24th-28th
Priority: Catch-up and Prepare for East St. Louis
May 1st-5th
Priority: Meet and Plan Presentation
Due: Power Pt Presentation