Plan of Execution
The Steps the Organization Needs to Accomplish Prior to Computer Delivery
- Wire room– this must be finished by April 25
- 7 gang boxes (see chart for where)-desk
- Conduit between secretary’s office and lab to pass the ethernet connection through
- 2 dedicated 20 amp circuits
- surge protector in circuit box
- Review plan proposal from GSLIS Project Team and make revisions ASAP– Finish this by March 26 ideally.
- Remove one of the doors to the computer room and put up drywall.
- Order printer and ship it to PrairieNet.
- Get right size and shape of tables. Each table must be sturdy enough to handle the weight of 2 monitors, 2 CPUs, and any textbooks or other materials that will be used by 2 computer users. [Note: the CPUs might be placed on the floor, but it is a good idea to ensure that the computer tables can support this additional weight].
- Upgrade to high speed internet– this must be finished by April 25.
The Steps the Project Team Needs to Accomplish Prior to Computer Delivery
- Provide recommendation for printer to buy. We will email you by March 30 with our recommendation.
- Refurbish computers and install Windows 98 and appropriate software.
- Ensure that computers will work with printer
- Determine amount of cabling required to network lab and any other hardware such as switches that we will need.
Potential Risks That Might Hinder Fully Accomplishing the Plan
- Electrical work not being finished on time
- No access to high speed internet