Plan of Execution
The Steps the Organization Needs to Accomplish Prior to Computer Delivery
This work to be accomplished prior to delivery of computers Dec 4-5, 2009
- 2) 20-amp circuits (one for each wall — left and right — which are currently on different circuits)
- Double-gang boxes along both the left and right walls spread out at 3 feet off the wall with the door, 9 feet off the wall, and 15 feet off the wall
- (2) double-gang boxes on the back wall
- Cat 5 cable run between the office and The Learning Center
- Non-plastic tables, at least 30 inches deep along left and right walls
- J-hooks below and at the rear of tables every one foot along left and right walls (to hold and protect cables)
- Internet connection
Resources GSLIS Will Provide for Technology Implementation
- 10 computer workstations including computer, monitor, keyboard and mouse
- Printer
- Recommendations for Internet service providers
- Installed open access operating system on all computer workstations
- Variety of open access software (Open Office Suite, others to be determined)
The Steps the Project Team Needs to Accomplish Prior to Computer Delivery
- Identify potential internet service providers
- Refurbish systems to be donated
- Identify free software to meet needs discussed in meeting
- Install software
Potential Risks That Might Hinder Fully Accomplishing the Plan
- Is affordable internet available at that location?
- Site could fail to complete above steps