Plan of Execution

The Steps the Organization Needs to Accomplish Prior to Computer Delivery

This work to be accomplished prior to delivery of computers Dec 4-5, 2009

  • 2) 20-amp circuits (one for each wall — left and right — which are currently on different circuits)
  • Double-gang boxes along both the left and right walls spread out at 3 feet off the wall with the door, 9 feet off the wall, and 15 feet off the wall
  • (2) double-gang boxes on the back wall
  • Cat 5 cable run between the office and The Learning Center
  • Non-plastic tables, at least 30 inches deep along left and right walls
  • J-hooks below and at the rear of tables every one foot along left and right walls (to hold and protect cables)
  • Internet connection

Resources GSLIS Will Provide for Technology Implementation

  • 10 computer workstations including computer, monitor, keyboard and mouse
  • Printer
  • Recommendations for Internet service providers
  • Installed open access operating system on all computer workstations
  • Variety of open access software (Open Office Suite, others to be determined)

The Steps the Project Team Needs to Accomplish Prior to Computer Delivery

  • Identify potential internet service providers
  • Refurbish systems to be donated
  • Identify free software to meet needs discussed in meeting
  • Install software

Potential Risks That Might Hinder Fully Accomplishing the Plan

  • Is affordable internet available at that location?
  • Site could fail to complete above steps