Implementation plan was based on a fluid and cooperative team approach, with very limited specialization of individuals or subgroups in particular tasks or skill groups.  This decision was based on the following factors:

  • Telescoped time frame for project completion/Large number of workstations: In order for the project to go forward, many of the tasks needed to be handled in a matter of hours and required all possible hands.
  • Scheduling complications of a large group: Due to inevitable schedule conflicts of seven individuals, group members  had to be prepared to work with other available team members on whatever task was most pressing
  • Dynamic input/feedback from in-house technology staff: Because workflow configuration at the lab depended on changeable input from Art and Don, team members needed to be prepared to adapt.

Task Schedule

Members of the team were present at LC, pursuant to project needs and to the schedules of LC staff (who needed to be present).  Main hours of work were Monday AM, Tuesday AM, Friday PM, Saturday, and Sunday (see schedule provided in appendix).

  • Task Description
  • Priority
  • Target Start Week
Target Completion Week Team Members Responsible
Unpacking of computers 8 9 9 Cassandra, Natalie, Logan, Erin
Basic test of viability of computers and hubs 8 9 9 Everybody
Removal and documentation of hard drives 7 9 9 Cassandra, Everybody
Testing and setup of electrical power 10 9 10 Cassandra, Natalie, Logan, Erin
Labeling of computers 7 9 9 Cassandra, Erin, Everybody
Design of network schematic 10 10 12 Logan, Josh, Randy, Everybody
Initial assessment of cabling needs 10 10 11 Cassandra, Logan
Cleanup of ceiling/excess cables 8 10 12 Everybody
Cable making and testing 10 10 12 Josh, Mark, Everybody
Implementation of network plan 10 10 11 Logan, Randy, Cassandra, Everybody
Configure server cabinet 10 9 12 Everybody
Testing of network connections 9 10 12 Natalie, Mark, Everybody
Copying of image onto hard drives 10 11 12 Everybody
Restoration of hard drives to original locations 10 11 12 Everybody
Enclosure of cables and cleanup 8 10 12 Everybody

Weekly Breakdown of Tasks

Week 9

  1. Meet with Art Hughes (AH) to clarify and coordinate plan (10/16)
  2. Unpack, arrange and begin testing computers.
  3. Remove and process hard drives, record serial numbers
  4. Assessment of electrical supply, and arrangement of cords/adapters.
  5. Initial attempt at image
  6. Discussion with AH about problem of noise from server, extracting cable from the ceiling, and setup of first five computers

Week 10

  1. Continue attempt at image
  2. Initial networking plan
  3. Calculation of cabling needs
  4. Continued testing of NIC cards and hubs
  5. Making cables for center island
  6. Begin process of trimming excess cables on door wall.
  7. Investigate connection between hubs

Week 11

  1. Continue trimming cables
  2. Continue cable assessment
  3. Making cables for window row
  4. Begin duping of image (incl. moving of jumpers) using provided disks
  5. Begin attaching labels to cables, matching workstation number

Week 12

  1. Continue duping
  2. Finish cable function confirmation
  3. Continue cleanup
  4. Wrapup meeting with AH