Prairienet Banner

Implementation Plan

Week 9-March 4-9

1. Visit Lessie Bates to determine the needs of the site.

2. Measure the space and map out electrical outlets.

3. Start the computers site already has to determine upgrades needed.

Week 10-Spring Break March 11-17

1. Meet for dinnner!

2. Create our plan that you see below!

Week 11-March 25-31

1.  Wipe computers and prepare for Win98 install.

2. Begin installation of Win98 on computers.

Week 12-April 1-7

1. Install Win98 on computers.

2. Load the correct drivers.

Week 13-April 8-14

1. Install drivers and updates on computers.

2. Search for educational software.

Week 14-April 15-21

1. Get that last computer to work!

2. Make 9 cables of various lengths.

Week 15-April 22-28

1. Still getting that last computer to work!

2. Gather mice and keyboards for 14 computers.

3. Install any educational software the group agrees on.